Contracts

oil and gas,contracts,upstream oil and gas contracts,oil and gas contracts master class,international oil and gas contracts,upstream oil and gas contracts online,upstream oil and gas contracts in dubai,upstream oil and gas contracts in paris,upstream oil and gas contracts in london,upstream oil and gas contracts in madrid,upstream oil and gas contracts in berlin,oil and gas contracts master class online,upstream oil and gas contracts in istanbul

                                                             

   Contracts

The actual well costs are divided into Fixed costs: casing and tubulars, logging, cementing, drill bits, mobilization charges, rig move Daily costs: contractor services, rig time, consumables Overheads: offices, salaries, pensions, health care, travel.

A fairly significant charge is usually made by the drilling contractor to modify and prepare the rig for a specific drilling campaign. This is known as a mobilization cost.

A similar charge will cover ‘once off’ expenses related to terminating the operations for a particular client and is called a demobilization cost. These costs can be significant, say 5–10 million US$.

 the actual costs of a well show considerable variations and are dependent on a number of factors, for example:

type of well (exploration, appraisal, development)

well trajectory (vertical, deviated, horizontal, multilateral)

total depth

subsurface environment (temperatures, pressures, corrosiveness of fluids)

type and rating of rig

type of operation (land, marine)

infrastructure available, transport and logistics

climate and geography (tropical, arctic, remoteness of location).

Most companies hire a drilling contractor to supply equipment and manpower rather than having their own rigs and crews. The reasons for this are threefold:

a considerable investment is required to build/buy a rig

rig and crew need to be maintained and paid regardless of the operational requirements and activities of the company

drilling contractors can usually operate more cheaply and efficiently than a company which carries out drilling operations as a non-core activity.

Before a contract is awarded a tender procedure is usually carried out. Thus, a number of suitable companies are invited to bid for a specified amount of work.

Bids will be evaluated based on price, rig specifications and the past performance of the contractor, with particular attention to their safety record. Several types of contracts are used.

1.1.          Turnkey contract

This type of contract requires the operator to pay a fixed amount to the contractor upon completion of the well, whilst the contractor furnishes all the material and labor and handles the drilling operations independently.

 The difficulty with this approach is to ensure that a ‘quality well’ is delivered to the company since the drilling contractor will want to drill as quickly and cheaply as possible.

The contractor therefore should guarantee an agreed measurable quality standard for each well. The guarantee should specify remedial actions which will be implemented should a substandard well be delivered.

1.2.          Footage contract

The contractor is paid per foot drilled. Whilst this will provide an incentive to ‘make hole’ quickly, the same risks are involved as in the turnkey contract.

 Footage contracts are often used for the section above the prospective reservoir where hole conditions are less crucial from an evaluation or production point of view.

1.3.          Incentive contract

This method of running drilling operations has been very successfully applied in recent years and has resulted in considerable cost savings. Various systems are in operation, usually providing a bonus for better than average performance.

 The contractor agrees with the company on the specifications for the well. Then the ‘historic’ cost of similar wells which have been drilled in the past is established. This allows estimation of the costs expected for the new well. The contractor will be entirely in charge of drilling the well, and cost savings achieved will be split between company and contractor.

1.4.          Day rate contract

As the name implies the company basically rents the rig and crew on a per day basis.

Usually, the oil company also manages the drilling operation and has full control over the drilling process.

This type of contract actually encourages the contractor to spend as much time as acceptable ‘on location’.

With increased cost consciousness, day rate contracts have become less favored by most oil companies.

Actual contracts often involve a combination of the above. For instance, an operator may agree to pay footage rates to a certain depth, day rates below that depth, and standby rates for days when the rig is on site, but not drilling.

1.5.          Partnering and alliances

In recent years, a new approach to contracting has evolved and is gaining rapid acceptance in the industry.

The concept has become known as partnering and can be seen as a progression of the incentive contract.

 Whilst the previously described contractual arrangements are restricted to a single well project or a small number of wells in which a contractor is paid by a client for the work performed, partnering describes the initiation of a long-term relationship between the asset holder (e.g. an oil company) and the service companies (e.g. drilling contractor and equipment suppliers).

 It includes the definition and merging of joint business objectives, the sharing of financial risks and rewards and is aimed at an improvement in efficiency and reduction of operating costs.

 Therefore, a partnering contract will not only address technical issues but also include business process quality management.

 The latter has proven to result in more efficient and economic use of resources, for instance the setting up of ‘joint implementation teams’ has replaced the practice of having separate teams in contractor and operator offices, essentially performing the same tasks.

The industry is increasingly acknowledging the value of contractors and service companies in improving their individual core capabilities through alliances, that is a joint venture for a particular project or a number of projects.

 A lead contractor, for example a drilling company, may form alliances with a number of subcontractors to be able to cover a wider spectrum of activities, for example completions, workovers and well interventions. 

تعليقات

المشاركات الشائعة من هذه المدونة

الفكر الاقتصادي في العصور الوسطى الأوروبية

العصور الوسطى الأوروبية: في القرون من التاسع حتى الخامس عشر الميلادية ساد في أوربا التكوين الاجتماعي الاقطاعي، وتتميز طريقة انتاجه التي بدأت في فرنسا ثم انتشرت في انجلترا وباقي مجتمعات أوروبا: ــ بأن العلاقات الاجتماعية للانتاج تدور أساسا حول الأرض التي تصبح البلورة المادية للملكية العقارية، اذ هي ترتكز على اقتصاد يغلب عليه الطابع الزراعي. ــ لمن يقومون بالعمل في الانمتاج الزراعي حق استعمال الأرض وشغلها. أما حق ملكيته فهو على درجات لهرم من السادة تحدده التقاليد والعادات. ــ هذا الأساس الاقتصادي يقابله شبكة من الروابط الشخصية، جزء من العاملين لا يتمتع بكامل حريته الشخصية حيث أنهم أقنان، أما السادة فيرتبط نظام ملكيتهم بنظام من الواجبات يتحمل بها كل منهم في مواجهة من هو أعلى منه. وتجد طريقة الانتاج هذه جذورها في المجتمع القديم حين بدأ كبار ملاك الأراضي يقاومون سلطة روما عن طريق الاقامة في ملكياتهم العقارية وتوسيع هذه الملكيات بالسيطرة على الملكيات الأصغر والمزارع المهجورة. في هذا النظام توجد جذور نظام الأقنان، غير أن هذا لا يعني أن القن وجد كنتيجة للتحرر الجزئي للعبد وانما ي...

مفهوم التخلف والدولة المتخلفة

لقد تعددت مسميات الدول الفقيرة فهناك من يطلق عليها الدول المتأخرة لأنها لم تصل الى مستوى مرتفع من التقدم الفني والاقتصادي , كما أطلق عليها الدول المتخلفة حيث تنخفض فيها مستويات المعيشة عن تلك المستويات السائدة في دول أوروبا , كما أطلق عيها الدول النامية حيث تقوم هذه الدول بمجهود انمائي , كما أطلق عليها أخيرا دول العالم الثالث حيث أن هذه الدول لا تمثل مجموعة متجانسة يمكن أن يشملها تعريف واحد. والحقيقة أنه لا يوجد أي فرق جوهري في هذه المسميات ولكننا سنتفق علي مصطلح الدول المتخلفة. أولا: مفهوم التخلف:- هناك ثلاث اتجاهات رئيسية لتعريف وتحديد التخلف نتناولهم كالآتي:- 1-                       الاتجاه الأول: يقوم هذا الاتجاه بحصر سمات ومظاهر التخلف المتمثلة في انخفاض متوسط الأجور ومستويات المعيشة والاستثمار وانتشار البطالة. ويركز هذا الاتجاه على انخفاض الدخل القومي مما يؤدي الى انخفاض متوسط دخل الفرد وذلك يؤدي الى انخفاض معدل الاشتثمار مما يؤدي الى انخفاض الدخل وبالتالي ترسيخ جذور ا...

نظرية الانتاج

نظرية الانتاج ـ الانتاج يتمثل في الجهد الانساني الذي يبذل لجعل الموارد الاقتصادية صالحة لاشباع الحاجات الانسانية، وهو جهد يتضمن علاقة مزدوجة. علاقة بين الانسان والطبيعة، وعلاقة بين الانسان والانسان. ـ تتطلب عملية الانتاج توافر العناصر الآتية: القوة العاملة وأدوات العمل وموضوع العمل. ـ تضم نظرية الانتاج موضوعات عديدة أهمها: عناصر الانتاج وكيفية التأليف بين هذه العناصر وأشكال المشروعات القائمة الانتاج، واتجاهات هذه المشروعات. ـ عناصر الانتاج وتسمى أيضا عناصر المشروع هي الموارد التي يستخدمها المجتمع في انتاج ما يحتاجه من سلع وخدمات، عناصر الانتاج أربعة: الطبيعة والعمل ورأس المال والتنظيم. ـ الموارد الطبيعية كعنصر من عناصر الانتاج هي كافة هبات الطبيعة التي لم يوجدها عمل انساني سابق ولا حاضر والتي تمكن الانسان من انتاج السلع والخدمات التي يحتاجها لاشباع حاجاته. ـ الطبيعة عنصر سلبي في الانتاج. ـ هناك عدة عوامل اساسية تحكم مدى كفاية الموارد الطبيعية لحاجة الانسان اليها للقيام بنشاطه الانتاجي وهي على سبيل الحصر: 1-          ...